Skip to content

Hydronic System Start Up

  1. Ensure all plumbing and wiring involving the CO2 HPWH and the Pod are correct and complete.

  2. Fill the tank by opening valves on lines B and F (see Plumbing System Diagram).

  3. Open PRV to allow air to exit the system. Leave open until water comes out of the relief valve.

  4. Open the remaining valves (see Plumbing System Diagram).

  5. Open the hot water faucets to bleed air from the house piping system. Close the hot water faucets after no air is seen in the water.

  6. Open the three water bleed valves on the CO2 HPWH. Two are on the water connections, and the third is underneath the heat pump. Close the bleed valves after no air is seen in the water.

  7. Power the CO2 HPWH outdoor unit.

    Upon powering on, a SANCO2 CO2 HPWH undergoes an automatic 5-minute air bleed cycle, displays “12:00” on the screen, and begins to run. The 5-minute air bleed cycle on a Reclaim CO2 HPWH is started via the Harvest App.

    Next, set up communication between the CO2 HPWH and the Pod for the connection type used in your wiring:

    Dry-contact (legacy) connection

    No additional programming is required on the heat pump.

    Modbus connection

    Program the Modbus communication settings on the SANCO2 GS5 control panel. Remove the top cover and lift out the controller to reach the keypad (see figure), then:

    SANCO2 GS5 control panel: UP/DOWN and ENTER keys, and how to access the controller
    SANCO2 GS5 control panel and how to access it.
    1. Press and hold the Up and Down keys together to enter Commissioning mode.
    2. Use the Up and Down keys to find the Communication Setting Mode [C_SE] and press ENTER.
    3. Use the Up/Down keys to toggle between Modbus Off and Modbus On, then press ENTER to confirm your choice.
    4. Use the Up and Down keys to find the Modbus ID Setting Mode [id ] and press ENTER.
    5. Use the Up/Down keys to set the Modbus ID to 1 and press ENTER to confirm the value.
    6. Hold the ENTER key for 10 seconds to exit Commissioning mode.

For the hydronic coil to operate, all air must be purged from the hydronic coil loop.

  1. Close the shut-off valve at the tank on line H (see Plumbing System Diagram).

  2. Open the Hose Bib (HB) drain on line H to purge the hydronic coil and circulation pump. Continue purging until no air more air bubbles are visible in the water.

  3. Close the drain and re-open the shut-off valve at the tank on line H.